Skip to main content

Status

When

  • Main South Road - Night Closures

    more info →

    Hours of Work: 7pm - 7am (closures)
    Locations: Main South Road between Country Road and Norman Road

    Until late December 2025 we’ll be undertaking asphalt and pavement works to the south of the project site.

  • Changed traffic Conditions - Main South Road temporary night closures

    more info →

    Hours of Work: 7pm and 7am
    Locations: Main South Road between Port Road and Aldinga Beach Road

    Over the coming weeks, several access changes and temporary road closures will be required to safely facilitate final construction and finishing works.

  • Temporary Closure - Northbound on and off ramps at Aldinga Interchange

    more info →

    Hours of Work: 7pm and 7am
    Locations: Main South Road at Aldinga Interchange

    Between 7pm and 7am, from Sunday 30 November for approximately two weeks, Northbound on and off ramps at the Aldinga Interchange will be closed individually at a time.

  • Changed Traffic Conditions - Sellicks Beach Road

    more info →

    Hours of Work: 24 hours a day
    Locations: Sellicks Beach Road

    From Tuesday 25 November until Friday 12 December 2025, Sellicks Beach Road between Main South Road and Forth Street will be closed 24 hours a day.

  • Changed Traffic Conditions - Intersection closures along Main South Road

    more info →

    Hours of Work: 24 hours a day
    Locations: Main South Road

    As we progress towards project completion, we’ll be undertaking final construction and finishing works at key intersections along Main South Road

  • Main South Road Duplication - Major Construction

    more info →

    Hours of Work: Until April 2026

    Works to duplicate Main South Road between Aldinga and Sellicks Beach will continue until April 2026. Works will generally be undertaken between the hours of 7am and 7pm Monday to Saturday.

Page 1 of 2
Next